FW: Essex Crossing Weekly Construction Updates Mar 14-19th 2016

 

 

 

Weekly Construction

Update

io Up

 

Mar 14-19th 2016

 

 

 

 

Lower East Side Residents:

To keep you informed of the construction activities at Essex Crossing, we will provide weekly site by site updates.  For more info regarding this work, please contact info@essexcrossingnyc.com. To opt out of these emails, please click unsubscribe on the link at the bottom of this email.

 

 

 

 

 

Site 1 (242 Broome Street)

 

This week Site 1 will placing the concrete mud slab. The concrete trucks and concrete pump will be located within the site. Drilling will begin for the sleeve for the elevator piston. The drill rig will also be located within the site gate. Flag persons will be positioned at the gate to direct pedestrian & vehicular traffic. Noise and dust control will be standard daily operations. No after-hours work in anticipated. 

 

Site 2 (115 Delancey Street)

 

Site 2 will continue excavation and support of excavation at the cellar and sub-cellar level. Sub-cellar and cellar concrete pile cap installation will continue this week. Both of these activities will continue on Saturday, March 19th between the hours of 9am-5pm.

 

Site 5 (145 Clinton Street)

 

Foundation and superstructure work continues at Site 5. Underground plumbing installations, with subsequent inspections, continue along with concrete installations. Concrete pours are anticipated to take place on Monday, March 14th and Thursday, March 17th in the early morning hours.  

 

Site 6 (175 Delancey Street)

 

The coming week's activity at Site 6 includes pouring concrete for the foundation on the west & south sides (Clinton & Delancey) and installing rebar and formwork for the east side foundation and interior columns. No after-hours work is scheduled.

 

 

Job Opportunities

Delancey Street Associates has partnered with workforce organizations the Lower East Side Employment Network (LESEN), a group of local agencies that assists Lower East Side and NYC residents to advance their careers and Workforce1,a service provided by the NYC Department of Small Business Services that prepares and connects qualified candidates to job opportunities in New York City. To register for construction related jobs and job training programs in several growth industries, including trainings to more successfully pursue temporary and permanent opportunities at Essex Crossing, please visit  http://bit.ly/constructioncareersnyc.

 

 

M/WBE Opportunities

Delancey Street Associates encourages Minority and Women Owned Business Enterprise (M/WBE) contractors to participate in the development of Essex Crossing across multiple trades. For more information about upcoming bid opportunities, as well as information about future M/WBE trade fairs, networking events and workshops related to the project, please fill out an inquiry form on our website.

 

 

You can visit the Essex Crossing News section for the latest project updates.

 

Delancey Street Associates, 419 Park Ave South, New York, NY 10016

 

 

Sent by info@essexcrossingnyc.com in collaboration with

 

Wednesday, March 9, 2016

FW: Leadership opportunity for high school sophomores

YouthBridge-NY is now accepting applications for the 2016-2018 fellowship class! Any potential teen leaders in the 10th grade are encouraged to apply!

View this email in your browser


Do you know of any 10th graders interested in learning more about diversity and issues affecting NYC? 
Share this opportunity with your students to help them become stronger leaders!


YouthBridge-NY is currently accepting applications

for the upcoming 2016-2018 Fellowship Year!

 

What should participants expect? ·       Gain leadership skills ·       Participate in diversity trainings ·       Community service projects ·       Meetings with influential NYC decision makers ·       Make new friends ·       Internship opportunities ·       Work with top student leaders from around NYC ·       Field trips and tours of local establishments

 

The deadline for applications is
Monday, March 28, 2016
Share this opportunity today!


Rolling admissions -- applications are considered in the order they are received -- don't delay! 

To learn more or apply now, visit our website: www.youthbridgeny.org/fellowship

For more information, email us at youthbridgeny@gmail.com or call (212) 983-4800 x145 

 

Copyright © 2016 YouthBridge-NY, All rights reserved.
We're switching over to MailChimp and transferring all our lists. We apologize if you do not wish to be included and you may opt out below.

Our mailing address is:

YouthBridge-NY

225 West 34th Street

Suite 1607

New York, NY 10122


Add us to your address book



unsubscribe from this list    update subscription preferences 

Email Marketing Powered by MailChimp

Monday, March 7, 2016

FW: Essex Crossing Weekly Construction Updates Mar 7-12th 2016

 

 

From: Delancey Street Associates [mailto:info@essexcrossingnyc.com]
Sent: Monday, March 07, 2016 8:04 AM
To: ksancimino@lomanyc.net
Subject: Essex Crossing Weekly Construction Updates Mar 7-12th 2016

 

 

 

Weekly Construction

Update

io Up

 

Mar 7-12th 2016

 

 

 

 

Lower East Side Residents:

To keep you informed of the construction activities at Essex Crossing, we will provide weekly site by site updates.  For more info regarding this work, please contact info@essexcrossingnyc.com. To opt out of these emails, please click unsubscribe on the link at the bottom of this email.

 

 

 

 

 

Site 1 (242 Broome Street)

 

Concrete placement will be conducted on site, no pump will be required. Flaggers will direct pedestrian and vehicular traffic as needed along Ludlow and Broome. No after-hours work is anticipated. 

 

Site 2 (115 Delancey Street)

 

Site 2 will continue excavation and support of excavation at the cellar and sub-cellar level. Sub-cellar concrete pile cap installation will continue this week. Both of these activities will continue on Saturday, March 12th between the hours of 9am-5pm.

 

Site 5 (145 Clinton Street)

 

Foundation and superstructure work continues at Site 5. Underground plumbing installations, with subsequent inspections, continue along with concrete installations. Concrete pours are anticipated to take place on Tuesday, March 8th and Thursday, March 10th in the early morning hours. 

 

Site 6 (175 Delancey Street)

 

The coming week's activity at Site 6 includes pouring concrete for the foundation on the south side (Broome Street) and installing rebar and formwork for the east side foundation. No after-hours work is scheduled.

 

 

Job Opportunities

Delancey Street Associates has partnered with workforce organizations the Lower East Side Employment Network (LESEN), a group of local agencies that assists Lower East Side and NYC residents to advance their careers and Workforce1,a service provided by the NYC Department of Small Business Services that prepares and connects qualified candidates to job opportunities in New York City. To register for construction related jobs and job training programs in several growth industries, including trainings to more successfully pursue temporary and permanent opportunities at Essex Crossing, please visit  http://bit.ly/constructioncareersnyc.

 

 

M/WBE Opportunities

Delancey Street Associates encourages Minority and Women Owned Business Enterprise (M/WBE) contractors to participate in the development of Essex Crossing across multiple trades. For more information about upcoming bid opportunities, as well as information about future M/WBE trade fairs, networking events and workshops related to the project, please fill out an inquiry form on our website.

 

 

You can visit the Essex Crossing News section for the latest project updates.

 

Delancey Street Associates, 419 Park Ave South, New York, NY 10016

 

 

Sent by info@essexcrossingnyc.com in collaboration with

 

Thursday, March 3, 2016

FW: Essex Crossing Weekly Construction Updates Feb 29th-Mar 5th 2016

 

 

Weekly Construction

Update

io Up

 

Feb 29-Mar 5 2016

 

 

 

 

Lower East Side Residents:

To keep you informed of the construction activities at Essex Crossing, we will provide weekly site by site updates.  For more info regarding this work, please contact info@essexcrossingnyc.com. To opt out of these emails, please click unsubscribe on the link at the bottom of this email.

 

 

 

 

 

Site 1 (242 Broome Street)

 

Site 1 will be grading and exporting soil in preparation for mud slab installation, which is anticipated to be placed on or about Thursday, March 3rd. Concrete trucks will enter site at the corner of Broome and Ludlow. Flaggers will be directing vehicular and pedestrian traffic along Ludlow and Broome. No after-hours work is expected at this time. 

 

Site 2 (115 Delancey Street)

 

Site 2 will continue excavation and support of the cellar and sub-cellar. Sub-cellar concrete pile cap installation will begin this week. Excavation and support of the cellar and sub-cellar levels will continue on Saturday, March 5th between the hours of 9am-5pm.

 

Site 5 (145 Clinton Street)

 

Foundation and superstructure work continues at Site 5. Underground plumbing installations, with subsequent inspections, continue along with concrete installations. A large concrete pour is anticipated to take place on Thursday, March 3rd in the early morning hours. 

 

Site 6 (175 Delancey Street)

 

The coming week's activity at Site 6 includes prepping for the cellar foundation walls and columns. No after-hours work is scheduled.

 

 

 

Job Opportunities

Delancey Street Associates has partnered with workforce organizations the Lower East Side Employment Network (LESEN), a group of local agencies that assists Lower East Side and NYC residents to advance their careers and Workforce1,a service provided by the NYC Department of Small Business Services that prepares and connects qualified candidates to job opportunities in New York City. To register for construction related jobs and job training programs in several growth industries, including trainings to more successfully pursue temporary and permanent opportunities at Essex Crossing, please visit  http://bit.ly/constructioncareersnyc.

 

 

M/WBE Opportunities

Delancey Street Associates encourages Minority and Women Owned Business Enterprise (M/WBE) contractors to participate in the development of Essex Crossing across multiple trades. For more information about upcoming bid opportunities, as well as information about future M/WBE trade fairs, networking events and workshops related to the project, please fill out an inquiry form on our website.

 

 

You can visit the Essex Crossing News section for the latest project updates.

 